# The Able Marine Energy Park Development Consent Order 2014, Paragraph 16

Extent: E+W+S

No licensed activity is to be carried out until 4 weeks after a vessel movement management plan has been agreed in writing by the MMO, and the licensed activities must be carried out in accordance with the vessel movement management plan.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/8/paragraph/16 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-8/paragraph-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.