The licence holder must ensure that—
(a) as a result of the capital dredging activities referred to in paragraph 11:
(i) no inerodible material and no more than 2,218,000 tonnes of erodible material site is disposed to site HU080; and
(ii) no erodible material and no more than 1,000,000 tonnes of inerodible material is disposed of to site HU082; and
(b) as a result of the maintenance dredging activities referred to in paragraph 12 no inerodible material and no more than 1,180,100 tonnes of erodible material per year is disposed to site HU080.

---