# The Able Marine Energy Park Development Consent Order 2014, Paragraph 48

Extent: E+W+S

(1) The licence holder must ensure that dredged material is passed through grid screens no larger than 30 centimetres to minimise the amount of man-made materials disposed of at sea.
(2) Any man-made material must be separated from the dredged material and disposed of to land.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/8/paragraph/48 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-8/paragraph-48
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

