# The Able Marine Energy Park Development Consent Order 2014, Paragraph 5

Extent: E+W+S

(1) The licence holder is permitted to construct and remove up to seven temporary dolphins within the berthing pocket, such that each dolphin comprises three tubular steel piles driven into the bed of the estuary from named plant moored in the estuary, after which the piles must be braced with interconnecting steelwork.
(2) Monitoring equipment fixed to buoys must be deployed at locations in the estuary during the piling works permitted by sub-paragraph (1) in accordance with the marine environmental management and monitoring plan referred to in paragraph 15.
(3) Each temporary dolphin must be removed as soon as practicable once the activities for which they have been constructed have been completed.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/8/paragraph/5 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-8/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.