# The Able Marine Energy Park Development Consent Order 2014, Paragraph 54

Extent: E+W+S

(1) The licence holder must employ methods to minimise resuspension of sediment during the construction and dredging operations.
(2) The methodology must be submitted to the MMO at least 4 weeks prior to the commencement of the works.
(3) Written approval by the MMO is required prior to works commencing.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/8/paragraph/54 (the official version)