# The Able Marine Energy Park Development Consent Order 2014, Paragraph 57

Extent: E+W+S

(1) The licence holder must monitor disposal site HU080 to ensure that the material is dispersing as predicted.
(2) A Monitoring Plan must be agreed in writing with the MMO at least 4 weeks prior to the commencement of works.
(3) The monitoring must be carried out in accordance with the Monitoring Plan agreed.

---