# The Able Marine Energy Park Development Consent Order 2014, Paragraph 60

Extent: E+W+S

(1) The licence holder must employ methods to minimise resuspension of sediment during dredging operations.
(2) The methodology must be submitted to the MMO at least 4 weeks prior to the commencement of the maintenance dredge.
(3) Written approval by the MMO to the methodology is required prior to the maintenance dredge commencing.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/8/paragraph/60 (the official version)