# The Able Marine Energy Park Development Consent Order 2014, Paragraph 64

Extent: E+W+S

(1) The licence holder must ensure that a full method statement and location of the transhipment area and barge approach routes is submitted to the MMO at least 4 weeks prior to the commencement of works.
(2) Written approval by the MMO is required prior to works commencing.

---