# The Able Marine Energy Park Development Consent Order 2014, Paragraph 8

Extent: E+W+S

The licence holder is permitted to remove a 250 metre section of the existing flood wall to create the Cherry Cobb Sands breach under the following conditions—
(a) the Cherry Cobb Sands breach must not be created until a new flood defence has been constructed landward of the existing flood defence;
(b) the Cherry Cobb Sands breach must not be created until a channel has been excavated from the site of the breach to the foreshore at the level of the breach; and
(c) all material is to be removed using land-based plant.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/8/paragraph/8 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-8/paragraph-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.