(1) The undertaker must not exercise the powers under any of the articles of the Order specified in sub-paragraph (2) over or in respect of the OCGT Order land otherwise than with the prior written consent of VPI.
(2) The articles referred to in sub-paragraph (1) are—
(a) article 15 (street works);
(b) article 16 (temporary stopping up of streets);
(c) article 17 (access to works);
(d) article 22 (authority to survey and investigate land);
(e) article 30 (compulsory acquisition of land);
(f) article 31 (power to override easements and other rights);
(g) article 34 (compulsory acquisition of rights etc.);
(h) article 35 (private rights of way);
(i) article 39 (rights under or over streets);
(j) article 40 (temporary use of land for carrying out the authorised development);
(k) article 41 (temporary use of land for maintaining authorised development); and
(l) article 42 (statutory undertakers).
(3) In the event that VPI withholds its consent pursuant to sub-paragraph (1) it must notify the undertaker in writing of the reasons for withholding such consent and (if applicable) the time period during which such consent will be withheld.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/9/paragraph/124 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-9/paragraph-124
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.