# The Able Marine Energy Park Development Consent Order 2014, Paragraph 76

Extent: E+W+S

In this Part of this Schedule—
“P66” means Phillips 66 Limited (Company number 00529086); and
“the pipelines” means the 4 pipelines crossing the Order land owned and operated by P66 used at various times for the passage of multi-purpose hydrocarbon fuels and all ancillary apparatus including such works and apparatus properly appurtenant to the pipelines as are specified by section 65(2) of the Pipe-Lines Act 1962.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/9/paragraph/76 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-9/paragraph-76
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.