In this Part of this Schedule—
“apparatus” means—
(a)in the case of an electricity undertaker, electric lines or electrical plant as defined in the Electricity Act 1989, belonging to or maintained by National Grid;
(b)in the case of a gas undertaker, any mains, pipes or other apparatus belonging to or maintained by a gas transporter for the purposes of gas supply;
“electric line” has the same meaning as contained in section 64(1) of the Electricity Act 1989;
“in” in a context referring to apparatus or alternative apparatus in land includes a reference to apparatus or alternative apparatus under, over, across, along or upon land;
“National Grid” means National Grid Plc, company number 4031152, registered at Grand Buildings, 1-3 Strand, London, WC2N 5EH, and includes any reference to National Grid Gas Plc.; and
“plans” include all designs, drawings, specifications, method statements, soil reports, programmes, calculations, risk assessments and other documents that are reasonably necessary properly and sufficiently to describe the works to be executed.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/9/paragraph/80 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-9/paragraph-80
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.