# The Able Marine Energy Park Development Consent Order 2014, Paragraph 86

Extent: E+W+S

If in consequence of the exercise of any powers under this Order the access to any apparatus is materially obstructed, the undertaker must provide such alternative means of access to such apparatus as will enable National Grid to maintain or use the apparatus no less effectively than was possible before such obstruction.

---
Source: https://www.legislation.gov.uk/uksi/2014/2935/schedule/9/paragraph/86 (the official version)
Page: https://openlegislation.uk/able-marine-energy-park-development-consent-order-2014/schedule-9/paragraph-86
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.