# The Access to the Countryside (Coastal Margin) (South Bents to Amble) Order 2018, Article 2: End of access preparation period


(1) In relation to land which is coastal margin as a result of the relevant approval, the day appointed as the day on which the access preparation period ends is 25th July 2018.
(2) In this article—
“the relevant approval” means the approval by the Secretary of State under section 52(1) of the Act of the relevant report on 31st October 2017;
“the relevant report” means the report entitled “Coastal Access South Bents to Amble” submitted by Natural England to the Secretary of State under sections 51 and 55A of the
Act on 24th March 2017

---