# Act of Sederunt (Rules of the Court of Session 1994) 1994, Paragraph 108.2: Declarations from the court that an EU instrument was invalid – notices


Where a party to the proceedings seeks a declaration from the court that an EU instrument was invalid on any of the grounds set out in the second paragraph of Article 263 TFEU as it has effect immediately before IP completion day, or the court is considering whether to make such a declaration at its own instance in the proceedings—
(a) notice in Form 108.2-A is to be given to the relevant UK authorities no later than 21 days, or such other period as the court may direct, before the date on which the declaration is to be made—
(i) by the party seeking the declaration; or
(ii) by the clerk of court,
as the case may be; and
(b) where notice is given by the party seeking the declaration, the party must lodge a certificate of notification in process.

---
Source: https://www.legislation.gov.uk/uksi/1994/1443/schedule/2/paragraph/108.2 (the official version)
Page: https://openlegislation.uk/act-of-sederunt-rules-of-the-court-of-session-1994-1994/schedule-2/paragraph-108.2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.