Article 6 Extension of time for doing work

Original text. Later amendments are not shown.

(1)

Where a tenant requires any question to be determined by arbitration under article 3 or 4, the time specified for doing the work which is the subject of the arbitration shall be extended until the termination of the arbitration.

(2)

Where the arbitrator finds that the tenant is liable to comply with a notice to do work or with any part of it, he shall extend the time for doing that work by such further period as he thinks fit.