Any dispute arising between the undertaker and the Environment Agency under this Schedule (other than a difference as to its meaning or construction) shall, if the parties agree, be determined by arbitration, but shall otherwise be determined by the Secretary of State for Environment, Food and Rural Affairs and the Secretary of State for Transport acting jointly on a reference to them by the undertaker or the Environment Agency, after notice in writing by one to the other.

---