(1)

The Authority may, when they have acquired the necessary land or sufficient rights therein, construct, continue and maintain on or under the land described in Schedule 1 to this Order the following works—

(a)

on the land described in paragraph 1 of the Schedule, a borehole on the site of the existing pumping station;

(b)

on the land described in paragraph 2 of the Schedule, a borehole together with a pumping station;

(c)

on the land described in paragraph 3 of the Schedule, a borehole;

(d)

(in addition to the works authorised by section 4 of the Third Schedule as applied to the undertaking by this Order) all such additional wells, boreholes, adits and headings as may be necessary or expedient for augmenting, improving or maintaining the supply of water obtainable by means of the said boreholes.

(2)

The works authorised by this Order shall for all purposes form part of the undertaking.