OpenLegislation

Paragraph 1

Changes not yet applied. Later legislation changes this provision in ways not yet written into the text below:

Premises and facilities must meet at least the following requirements:

(a)

the premises must be adequately separated from the public highway and other premises. Notwithstanding this they may occupy the same building as a slaughterhouse provided that they are in a completely separate part of the building; unauthorised persons and animals shall have no access to the premises;

(b)

the premises must have a clean and an unclean section, adequately separated. The unclean section must have a covered place to receive the material for rendering and must be constructed in such a way that it is easy to clean and disinfect. Floors must be laid in such a way as to facilitate the draining of liquids. The premises must have adequate lavatories, changing rooms and washbasins for staff;

in the unclean section, where appropriate, there must be adequate facilities for deskinning or de-hairing of animals and a storage room for hides;

(c)

the premises must have sufficient capacity and hot water and steam production for the rendering of material in accordance with Section B of Part I of this Schedule;

(d)

the unclean section must, if appropriate, contain equipment to reduce the size of material for rendering and equipment for loading the crushed material into the rendering unit;

(e)

a closed rendering installation is required in which the material must be rendered in accordance with Section B of Part I of this Schedule. Where heat treatment is required, this installation must be equipped with:

  • measuring equipment to check temperature and, if necessary, pressure at critical points;

  • recording devices to record continuously the results of measurements;

  • an adequate safety system to prevent insufficient heating;

(f)

to prevent recontamination of the finished rendered material by incoming raw material, there must be clear separation between the area of the premises where the incoming raw material is unloaded and rendered and the areas set aside for further processing of the heated material and the storage of the finished rendered product.