# The Associated British Ports (Grimsby Riverside Ro-Ro Terminal) Harbour Revision Order 2011, Article 5: Power to make subsidiary works

Extent: E+W+S

A.B. Ports may from time to time within the limits of deviation erect, construct and maintain all such works, conveniences, appliances and apparatus as they from time to time deem necessary or convenient for the purposes of or in connection with or incidental to, the construction and maintenance of the works or the accommodation of vessels at the works.

---
Source: https://www.legislation.gov.uk/uksi/2011/950/article/5 (the official version)