# The Associated British Ports (Hull) Harbour Revision Order 2006, Paragraph 10: Construction restrictions


The dredging of the berth area adjoining the quay face of Work No. 1 shall not be carried out until after completion of the noise barrier authorised by article 5(2) above.

---