# The Associated British Ports (Hull) Harbour Revision Order 2006, Paragraph 2: Planning restrictions


(1) In their application to the works, article 3 of, and Part 11 of Schedule 2 to, the 1995 Order shall have effect as if the planning permission granted by that Order were subject to the restrictions contained in paragraphs 3 to 11 below.
(2) In their application to other development carried out on land which falls to be treated as operational land of a dock or harbour undertaker by virtue of this Order, article 3 of, and Part 17 of Schedule 2 to, the 1995 Order shall have effect as if the planning permission granted by that Order, were subject to the restrictions contained in paragraphs 3 to 11 below.
(3) The restrictions contained in paragraphs 3 to 8 below do not apply to temporary construction activity.
(4) For the purpose of the Town and Country Planning Act 1990, the restrictions contained in paragraphs 3 to 11 below shall be deemed to be conditions imposed on the grant of planning permission.

---
Source: https://www.legislation.gov.uk/uksi/2006/1135/schedule/1/paragraph/2 (the official version)
Page: https://openlegislation.uk/associated-british-ports-hull-harbour-revision-order-2006/schedule-1/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.