# The Associated British Ports (Hull) Harbour Revision Order 2006, Paragraph 7: Operational restrictions


(1) Before the commencement of operations at the site, and for so long as such operations continue, A.B. Ports shall provide and maintain the noise barrier authorised by article 5(2) at a height of 5 metres above the level of Work No. 1.
(2) In sub-paragraph (1), “the site” has the meaning given by paragraph 8(4) below.

---
Source: https://www.legislation.gov.uk/uksi/2006/1135/schedule/1/paragraph/7 (the official version)
Page: https://openlegislation.uk/associated-british-ports-hull-harbour-revision-order-2006/schedule-1/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.