# The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024, Paragraph 1: Interpretation

Extent: E+W

In this Part of this Schedule—
“drainage strategy” means the document of that description annexed to the flood risk assessment as approved by the Board;
“Enhanced Operational Controls” means the controls set out in the document of that description listed in Schedule 7 (plans and documents to be certified) and certified by the Secretary of State as the Enhanced Operational Controls for the purposes of this Order;
“flood risk assessment” means the document of that description in Schedule 7 (plans and documents to be certified) certified by the Secretary of State as the flood risk assessment for the purposes of this Order;
“impact protection measures” means—
(a)part (a) of Work No.3 as defined in Schedule 1 to this Order; or
(b)part (b) of Work No. 3 as defined in Schedule 1 to this Order; or
(c)both parts (a) and (b) of Work No. 3 as defined in Schedule 1 to this Order;
“IOT” means the Immingham Oil Terminal;
“IOT Operators” means Associated Petroleum Terminals (Immingham) Ltd and Humber Oil Terminal Trustees Ltd, with “Associated Petroleum Terminals (Immingham) Ltd” meaning Associated Petroleum Terminals (Immingham) Limited, company number (00564394) registered at Queens Road, Immingham, Grimsby, N E Lincolnshire, DN40 2PN, and any successor in title and “Humber Oil Terminal Trustees Ltd” meaning Humber Oil Terminal Trustees Limited, company number (00874993) registered at Queens Road, Immingham, Grimsby, N E Lincolnshire, DN40 2PN, and any successor in title
“National Highways” means National Highways Limited (company number 09346363) whose registered office is Bridge House, 1 Walnut Tree Close, Guildford, Surrey GU1 4LZ or any such successor or replacement body that may from time to time be primarily responsible for the functions, duties and responsibilities currently exercised by that statutory body;
“operational freight management plan” means the document of that description listed in Schedule 7 (plans and documents to be certified) and certified by the Secretary of State as the ‘operational freight management plan’ for the purposes of this Order;
“outline onshore construction environmental management plan” means the document of that description in Schedule 7 (plans and documents to be certified) and certified by the Secretary of State as the outline onshore construction environmental management plan for the purposes of this Order; and
“travel plan” means the document of that description listed in Schedule 7 (plans and documents to be certified) and certified by the Secretary of State as the ‘travel plan’ for the purposes of this Order.

---
Source: https://www.legislation.gov.uk/uksi/2024/1014/schedule/2/paragraph/1 (the official version)