# The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024, Paragraph 11: Woodland management

Extent: E+W

The operation of the authorised development must not be commenced until a final version of the WEMP has been submitted to and approved in writing by the Council. The authorised development must be implemented in accordance with the approved WEMP.

---
Source: https://www.legislation.gov.uk/uksi/2024/1014/schedule/2/paragraph/11 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-eastern-ro-ro-terminal-development-consent-order-2024/schedule-2/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.