# The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024, Paragraph 19: Impact Protection Measures for the IOT finger pier

Extent: E+W

(1) Prior to the commencement of the commercial operation of Berth 1, using the berth numbering adopted on General Arrangements Plan B2429400-JAC-00-ZZ-DR-ZZ-0202 Revision P05, the undertaker must—
(a) notify the Statutory Conservancy and Navigation Authority, the dock master, the MMO and IOT Operators of its intention to install the impact protection measures comprising Work No. 3(b);
(b) agree a programme of works with the parties identified in sub-paragraph (a) above; and
(c) install the impact protection measures detailed as Work No. 3(b).

---
Source: https://www.legislation.gov.uk/uksi/2024/1014/schedule/2/paragraph/19 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-eastern-ro-ro-terminal-development-consent-order-2024/schedule-2/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.