# The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024, Paragraph 23: Further information regarding requirements

Extent: E+W

(1) In relation to any application referred to in paragraph 22, the discharging authority may request such further information from the undertaker as it considers necessary to enable it to consider the application.
(2) If the discharging authority considers that further information is necessary, the discharging authority must, within 24 business days of receipt of the application, notify the undertaker in writing specifying the further information required or must do so within any longer period as may be agreed in writing between the undertaker and the discharging authority.
(3) If the discharging authority does not give the notification within the period specified in subparagraph (2) it is deemed to have sufficient information to consider the application and is not entitled to request further information without the prior agreement of the undertaker.

---
Source: https://www.legislation.gov.uk/uksi/2024/1014/schedule/2/paragraph/23 (the official version)