# The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024, Paragraph 6: Piling and marine construction works restrictions

Extent: E+W

(1) Piling and marine construction works may be undertaken 24 hours a day on Mondays to Sundays provided that such works are undertaken in accordance with paragraph 12 of Part 2 of Schedule 3 (deemed marine licence).
(2) Any emergency works carried out in accordance with paragraph 12 of Part 2 of Schedule 3 must be notified to the Council within 72 hours of their commencement.
(3) Works for the capital dredge, which has the same meaning as in paragraph 1(1)(b) of Part 1 of Schedule 3, may be undertaken without restriction as to time or day.

---
Source: https://www.legislation.gov.uk/uksi/2024/1014/schedule/2/paragraph/6 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-eastern-ro-ro-terminal-development-consent-order-2024/schedule-2/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.