(1) Construction of—
(a) the terminal building and the welfare building for HGV drivers and passengers awaiting embarkation and related ancillary buildings as identified as part of Work No. 5(c);
(b) the proposed administrative and inspection buildings for UK Border Force as identified as Work No. 5(e); and
(c) the proposed ancillary buildings as identified as part of Work No. 4(f),
must not be commenced until the details of the location, heights relative to the proposed finished ground levels, and external materials to be used in the construction of all new permanent buildings and structures, including the colour, materials and finishes, have been submitted to and approved in writing by the Council.
(2) The authorised development must be implemented in accordance with the details approved by the Council.
(3) The authorised development must be carried out in accordance with the general arrangement plans.
(4) The authorised development will not be in accordance with the general arrangement plans if any departure from the general arrangement plans would give rise to any materially new or materially different environmental effects in comparison with those reported in the environmental statement.

---
Source: https://www.legislation.gov.uk/uksi/2024/1014/schedule/2/paragraph/7 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-eastern-ro-ro-terminal-development-consent-order-2024/schedule-2/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.