# The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024, Paragraph 142: Interpretation

Extent: E+W

The fact that any work or thing has been executed or done by the undertaker in accordance with a plan approved or deemed to be approved by the Board, or to its satisfaction, or in accordance with any directions or award of an arbitrator, does not relieve the undertaker from any liability under this Part of this Schedule.

---
Source: https://www.legislation.gov.uk/uksi/2024/1014/schedule/4/paragraph/142 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-eastern-ro-ro-terminal-development-consent-order-2024/schedule-4/paragraph-142
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

