# The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024, Paragraph 42: Application

Extent: E+W

For the protection of Northern Powergrid the following provisions, unless otherwise agreed in writing between the undertaker and Northern Powergrid, have effect for the duration of the construction of the authorised works, including (for the avoidance of doubt)—
(a) where this Order is amended by way of supplementary order, then the following provisions have effect for the construction of the development authorised by such supplementary order; and
(b) where a diversion or replacement of Northern Powergrid’s apparatus is required during the construction phase of this Order or any supplementary order, the following provisions have effect for as long as it takes for the diversion or replacement to be completed.

---
Source: https://www.legislation.gov.uk/uksi/2024/1014/schedule/4/paragraph/42 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-eastern-ro-ro-terminal-development-consent-order-2024/schedule-4/paragraph-42
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.