# The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024, Paragraph 91: Interpretation

Extent: E+W

Without limitation on the scope of paragraph 90 the requirements which North East Lincolnshire Council may make include conditions requiring the undertaker at its own expense to construct such protective works, whether temporary or permanent, before or during the construction of the specified works (including any new works as well as alterations to existing works) as are reasonably necessary—
(a) to safeguard any drainage work against damage; or
(b) to secure that the efficiency of any ordinary watercourse for flood defence or land drainage purposes is not impaired and that the risk of flooding is not otherwise increased,
by reason of the specified work.

---
Source: https://www.legislation.gov.uk/uksi/2024/1014/schedule/4/paragraph/91 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-eastern-ro-ro-terminal-development-consent-order-2024/schedule-4/paragraph-91
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.