# The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024, Paragraph 93: Interpretation

Extent: E+W

(1) Subject to sub-paragraph 2 the undertaker must from the commencement of the construction of the specified works maintain in good repair and condition and free from obstruction any drainage work which is situated within the limits of deviation and on land held by the undertaker for the purposes of or in connection with the specified works, whether or not the drainage work is constructed under the powers conferred by this Order or is already in existence.
(2) If any such drainage work which the undertaker is liable to maintain is not maintained to the reasonable satisfaction of North East Lincolnshire Council it may by notice in writing require the undertaker to repair and restore the work, or any part of such work, or (if the undertaker so elects and North East Lincolnshire Council in writing consents, such consent not to be unreasonably withheld or delayed), to remove the work and restore the site to its former condition, to such extent and within such limits as North East Lincolnshire Council reasonably requires.
(3) Subject to sub-paragraph 4 and paragraph 90, if, within a reasonable period being not less than 28 days beginning with the date on which a notice in respect of any drainage work is served under sub-paragraph (2) on the undertaker, the undertaker has failed to begin taking steps to comply with the reasonable requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, North East Lincolnshire Council may do what is necessary for such compliance and may recover any expenditure reasonably incurred by it in so doing from the undertaker.
(4) In the event of any dispute as to the reasonableness of any requirement of a notice served under sub-paragraph 2, North East Lincolnshire Council must not, except in a case of an emergency, exercise the powers conferred by sub-paragraph 3 until the dispute has been finally determined.
(5) This paragraph does not apply to—
(a) drainage works which are vested in North East Lincolnshire Council, or which North East Lincolnshire Council or another person is liable to maintain and is not precluded by the powers of the Order from doing so; and
(b) any obstruction of a drainage work for the purpose of a work or operation authorised by this Order and carried out in accordance with the provisions of this Part of this Schedule.

---
Source: https://www.legislation.gov.uk/uksi/2024/1014/schedule/4/paragraph/93 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-eastern-ro-ro-terminal-development-consent-order-2024/schedule-4/paragraph-93
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.