# The Associated British Ports (Immingham Green Energy Terminal) Order 2025, Article 9: Power to alter layout, etc., of streets

Extent: E+W+S

(1) The undertaker may, for the purposes of the authorised project, alter the layout of or carry out any works in the street—
(a) in the case of the streets specified in columns (1) and (2) of the table in Part 1 (permanent alteration of layout) of Schedule 5 (alteration of streets) permanently in the manner specified in relation to that street in column (3); and
(b) in the case of the streets specified in columns (1) and (2) of the table in Part 2 (temporary alteration of layout) of Schedule 5 temporarily in the manner specified in relation to that street in column (3).
(2) Without limitation on the specific powers conferred by paragraph (1) but subject to paragraphs (3) and (4), the undertaker may, for the purposes of constructing, operating, maintaining or decommissioning the authorised project, permanently or temporarily alter the layout of any street (and carry out works ancillary to such alterations) whether or not within the Order limits and the layout of any street having a junction with such a street and, without limiting the scope of this paragraph, the undertaker may—
(a) increase the width of the carriageway of the street by reducing the width of any kerb, footpath, footway, cycle track, central reservation or verge within the street;
(b) alter the level or increase the width of any such kerb, footpath, footway, cycle track, central reservation or verge;
(c) reduce the width of the carriageway of the street;
(d) execute any works to widen or alter the alignment of pavements;
(e) make and maintain crossovers and passing places;
(f) execute any works of surfacing or resurfacing of the highway;
(g) carry out works for the provision or alteration of parking places, loading bays and cycle tracks;
(h) execute any works related to signage and street markings;
(i) execute any works necessary to alter or provide facilities for the management and protection of pedestrians; and
(j) execute any works to provide or improve sight lines required by the highway authority.
(3) The undertaker must restore to the reasonable satisfaction of the street authority any street that has been temporarily altered under this article.
(4) The powers conferred by paragraph (2) may not be exercised without the consent of the street authority, which may attach any reasonable conditions to any consent but such consent is not to be unreasonably withheld or delayed.

---
Source: https://www.legislation.gov.uk/uksi/2025/165/article/9 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.