  "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/enacted",
  "json_url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/enacted.json",
  "id": "uksi/2025/165",
  "title": "The Associated British Ports (Immingham Green Energy Terminal) Order 2025",
  "short_title": "Associated British Ports (Immingham Green Energy Terminal) 2025",
  "long_title": "This Order grants development consent for and authorises the construction, operation and maintenance of a new liquid bulk import terminal and associated development within the Port of Immingham and to carry out all associated works.",
  "citation": "S.I. 2025/165",
  "type": "uksi",
  "year": "2025",
  "number": "165",
  "version": "enacted",
  "date": "2025-02-06",
  "revised": true,
  "valid_from": "2025-07-02",
  "extent": "E+W+S",
  "unapplied_effects": 0,
  "provisions": [
    {
      "path": "introduction",
      "kind": "introduction",
      "number": null,
      "heading": "Introductory text",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/introduction/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "part/1",
      "kind": "part",
      "number": "1",
      "heading": "PRELIMINARY",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "article/1",
      "kind": "article",
      "number": "1",
      "heading": "Citation and commencement",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/1"
    },
    {
      "path": "article/2",
      "kind": "article",
      "number": "2",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-2/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/1"
    },
    {
      "path": "article/3",
      "kind": "article",
      "number": "3",
      "heading": "Disapplication of legislative provisions",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-3/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/1"
    },
    {
      "path": "article/4",
      "kind": "article",
      "number": "4",
      "heading": "Incorporation of the 1847 Act",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-4/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/1"
    },
    {
      "path": "part/2",
      "kind": "part",
      "number": "2",
      "heading": "WORKS PROVISIONS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "part/2/crossheading/principal-powers",
      "kind": "crossheading",
      "number": null,
      "heading": "Principal powers",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2"
    },
    {
      "path": "article/5",
      "kind": "article",
      "number": "5",
      "heading": "Development consent, etc. granted by the Order",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-5/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/principal-powers"
    },
    {
      "path": "article/6",
      "kind": "article",
      "number": "6",
      "heading": "Extent of certain works",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-6/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/principal-powers"
    },
    {
      "path": "part/2/crossheading/streets",
      "kind": "crossheading",
      "number": null,
      "heading": "Streets",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2"
    },
    {
      "path": "article/7",
      "kind": "article",
      "number": "7",
      "heading": "Street works",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-7/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/streets"
    },
    {
      "path": "article/8",
      "kind": "article",
      "number": "8",
      "heading": "Application of the 1991 Act",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-8/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/streets"
    },
    {
      "path": "article/9",
      "kind": "article",
      "number": "9",
      "heading": "Power to alter layout, etc., of streets",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-9/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/streets"
    },
    {
      "path": "article/10",
      "kind": "article",
      "number": "10",
      "heading": "Construction and maintenance of new, altered or diverted streets and other structures",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-10/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/streets"
    },
    {
      "path": "article/11",
      "kind": "article",
      "number": "11",
      "heading": "Permanent stopping up of streets",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-11/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/streets"
    },
    {
      "path": "article/12",
      "kind": "article",
      "number": "12",
      "heading": "Permanent stopping up of public rights of way",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-12/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/streets"
    },
    {
      "path": "article/13",
      "kind": "article",
      "number": "13",
      "heading": "Temporary stopping up and prohibition or restriction of use of streets and public rights of way",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-13/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/streets"
    },
    {
      "path": "article/14",
      "kind": "article",
      "number": "14",
      "heading": "Use of private roads for construction",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-14/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/streets"
    },
    {
      "path": "article/15",
      "kind": "article",
      "number": "15",
      "heading": "Access to works",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-15/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/streets"
    },
    {
      "path": "article/16",
      "kind": "article",
      "number": "16",
      "heading": "Agreements with street authorities",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-16/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/streets"
    },
    {
      "path": "article/17",
      "kind": "article",
      "number": "17",
      "heading": "Apparatus and rights of statutory undertakers in stopped up streets",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-17/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/streets"
    },
    {
      "path": "part/2/crossheading/supplementary",
      "kind": "crossheading",
      "number": null,
      "heading": "Supplementary",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2"
    },
    {
      "path": "article/18",
      "kind": "article",
      "number": "18",
      "heading": "Discharge of water",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-18/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/supplementary"
    },
    {
      "path": "article/19",
      "kind": "article",
      "number": "19",
      "heading": "Authority to survey and investigate the land",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-19/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/supplementary"
    },
    {
      "path": "article/20",
      "kind": "article",
      "number": "20",
      "heading": "Protective works",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-20/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/supplementary"
    },
    {
      "path": "article/21",
      "kind": "article",
      "number": "21",
      "heading": "Removal of human remains",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-21/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/2/crossheading/supplementary"
    },
    {
      "path": "part/3",
      "kind": "part",
      "number": "3",
      "heading": "ACQUISITION AND POSSESSION OF LAND",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "part/3/crossheading/powers-of-acquisition",
      "kind": "crossheading",
      "number": null,
      "heading": "Powers of acquisition",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3"
    },
    {
      "path": "article/22",
      "kind": "article",
      "number": "22",
      "heading": "Compulsory acquisition of land",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-22/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/powers-of-acquisition"
    },
    {
      "path": "article/23",
      "kind": "article",
      "number": "23",
      "heading": "Time limit for exercise of powers to acquire land compulsorily or to possess land temporarily",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-23/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/powers-of-acquisition"
    },
    {
      "path": "article/24",
      "kind": "article",
      "number": "24",
      "heading": "Compulsory acquisition of rights and restrictive covenants",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-24/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/powers-of-acquisition"
    },
    {
      "path": "article/25",
      "kind": "article",
      "number": "25",
      "heading": "Acquisition of subsoil or airspace only",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-25/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/powers-of-acquisition"
    },
    {
      "path": "article/26",
      "kind": "article",
      "number": "26",
      "heading": "Private rights",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-26/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/powers-of-acquisition"
    },
    {
      "path": "article/27",
      "kind": "article",
      "number": "27",
      "heading": "Power to override easements and other rights",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-27/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/powers-of-acquisition"
    },
    {
      "path": "article/28",
      "kind": "article",
      "number": "28",
      "heading": "Rights over or under streets",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-28/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/powers-of-acquisition"
    },
    {
      "path": "article/29",
      "kind": "article",
      "number": "29",
      "heading": "Application of the 1981 Act",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-29/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/powers-of-acquisition"
    },
    {
      "path": "article/30",
      "kind": "article",
      "number": "30",
      "heading": "Modification of Part 1 of the 1965 Act",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-30/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/powers-of-acquisition"
    },
    {
      "path": "part/3/crossheading/temporary-possession-of-land",
      "kind": "crossheading",
      "number": null,
      "heading": "Temporary possession of land",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3"
    },
    {
      "path": "article/31",
      "kind": "article",
      "number": "31",
      "heading": "Temporary use of land for constructing the authorised project",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-31/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/temporary-possession-of-land"
    },
    {
      "path": "article/32",
      "kind": "article",
      "number": "32",
      "heading": "Temporary use of land for maintaining the authorised project",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-32/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/temporary-possession-of-land"
    },
    {
      "path": "part/3/crossheading/supplementary",
      "kind": "crossheading",
      "number": null,
      "heading": "Supplementary",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3"
    },
    {
      "path": "article/33",
      "kind": "article",
      "number": "33",
      "heading": "Statutory undertakers",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-33/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/supplementary"
    },
    {
      "path": "article/34",
      "kind": "article",
      "number": "34",
      "heading": "Recovery of costs of new connections",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-34/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/supplementary"
    },
    {
      "path": "article/35",
      "kind": "article",
      "number": "35",
      "heading": "Acquisition of part of certain properties",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-35/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/supplementary"
    },
    {
      "path": "article/36",
      "kind": "article",
      "number": "36",
      "heading": "Compulsory acquisition of land – incorporation of the mineral code",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-36/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/supplementary"
    },
    {
      "path": "part/3/crossheading/compensation",
      "kind": "crossheading",
      "number": null,
      "heading": "Compensation",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3"
    },
    {
      "path": "article/37",
      "kind": "article",
      "number": "37",
      "heading": "Disregard of certain interests and improvements",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-37/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/compensation"
    },
    {
      "path": "article/38",
      "kind": "article",
      "number": "38",
      "heading": "Set-off for enhancement in value of retained land",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-38/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/compensation"
    },
    {
      "path": "article/39",
      "kind": "article",
      "number": "39",
      "heading": "No double recovery",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-39/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/3/crossheading/compensation"
    },
    {
      "path": "part/4",
      "kind": "part",
      "number": "4",
      "heading": "OPERATIONAL PROVISIONS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "article/40",
      "kind": "article",
      "number": "40",
      "heading": "Authorisation of operation and use",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-40/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/4"
    },
    {
      "path": "article/41",
      "kind": "article",
      "number": "41",
      "heading": "Maintenance of authorised project",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-41/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/4"
    },
    {
      "path": "article/42",
      "kind": "article",
      "number": "42",
      "heading": "Limits of dock master’s jurisdiction",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-42/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/4"
    },
    {
      "path": "article/43",
      "kind": "article",
      "number": "43",
      "heading": "Area of jurisdiction to form part of the undertaking and application of byelaws",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-43/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/4"
    },
    {
      "path": "article/44",
      "kind": "article",
      "number": "44",
      "heading": "Power to appropriate",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-44/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/4"
    },
    {
      "path": "article/45",
      "kind": "article",
      "number": "45",
      "heading": "Powers to dredge",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-45/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/4"
    },
    {
      "path": "part/5",
      "kind": "part",
      "number": "5",
      "heading": "MISCELLANEOUS AND GENERAL",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "article/46",
      "kind": "article",
      "number": "46",
      "heading": "Benefit of Order",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-46/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/47",
      "kind": "article",
      "number": "47",
      "heading": "Deemed marine licence",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-47/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/48",
      "kind": "article",
      "number": "48",
      "heading": "Saving for Trinity House",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-48/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/49",
      "kind": "article",
      "number": "49",
      "heading": "Provision against danger to navigation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-49/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/50",
      "kind": "article",
      "number": "50",
      "heading": "Lights on tidal works during construction",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-50/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/51",
      "kind": "article",
      "number": "51",
      "heading": "Permanent light on tidal works",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-51/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/52",
      "kind": "article",
      "number": "52",
      "heading": "Application of landlord and tenant law",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-52/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/53",
      "kind": "article",
      "number": "53",
      "heading": "Felling or lopping of trees and removal of hedgerows",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-53/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/54",
      "kind": "article",
      "number": "54",
      "heading": "Trees subject to tree preservation orders",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-54/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/55",
      "kind": "article",
      "number": "55",
      "heading": "Planning legislation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-55/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/56",
      "kind": "article",
      "number": "56",
      "heading": "Traffic regulation measures",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-56/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/57",
      "kind": "article",
      "number": "57",
      "heading": "Defence to proceedings in respect of statutory nuisance",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-57/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/58",
      "kind": "article",
      "number": "58",
      "heading": "Protection of interests",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-58/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/59",
      "kind": "article",
      "number": "59",
      "heading": "Crown rights",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-59/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/60",
      "kind": "article",
      "number": "60",
      "heading": "Application of sections 91(3A) and (3B) of the 1990 Act",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-60/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/61",
      "kind": "article",
      "number": "61",
      "heading": "Arbitration",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-61/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/62",
      "kind": "article",
      "number": "62",
      "heading": "Procedure regarding certain approvals, etc.",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-62/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/63",
      "kind": "article",
      "number": "63",
      "heading": "Certification of documents, public register, etc.",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-63/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "article/64",
      "kind": "article",
      "number": "64",
      "heading": "Service of notices",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/article-64/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "part/5"
    },
    {
      "path": "signature",
      "kind": "signature",
      "number": null,
      "heading": "Signature",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/signature/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/1",
      "kind": "schedule",
      "number": "1",
      "heading": "AUTHORISED PROJECT",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/1/part/1",
      "kind": "part",
      "number": "1",
      "heading": "AUTHORISED DEVELOPMENT",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/part-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1"
    },
    {
      "path": "schedule/1/part/1/crossheading/nationally-significant-infrastructure-project",
      "kind": "crossheading",
      "number": null,
      "heading": "Nationally significant infrastructure project",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1"
    },
    {
      "path": "schedule/1/paragraph/1",
      "kind": "paragraph",
      "number": "1",
      "heading": "Work No. 1",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1/crossheading/nationally-significant-infrastructure-project"
    },
    {
      "path": "schedule/1/part/1/crossheading/associated-development",
      "kind": "crossheading",
      "number": null,
      "heading": "Associated development",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1"
    },
    {
      "path": "schedule/1/paragraph/2",
      "kind": "paragraph",
      "number": "2",
      "heading": "Work No. 2",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-2/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1/crossheading/associated-development"
    },
    {
      "path": "schedule/1/paragraph/3",
      "kind": "paragraph",
      "number": "3",
      "heading": "Work No. 3",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-3/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1/crossheading/associated-development"
    },
    {
      "path": "schedule/1/paragraph/4",
      "kind": "paragraph",
      "number": "4",
      "heading": "Work No. 4",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-4/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1/crossheading/associated-development"
    },
    {
      "path": "schedule/1/paragraph/5",
      "kind": "paragraph",
      "number": "5",
      "heading": "Work No. 5",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-5/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1/crossheading/associated-development"
    },
    {
      "path": "schedule/1/paragraph/6",
      "kind": "paragraph",
      "number": "6",
      "heading": "Work No. 6",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-6/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1/crossheading/associated-development"
    },
    {
      "path": "schedule/1/paragraph/7",
      "kind": "paragraph",
      "number": "7",
      "heading": "Work No. 7",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-7/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1/crossheading/associated-development"
    },
    {
      "path": "schedule/1/paragraph/8",
      "kind": "paragraph",
      "number": "8",
      "heading": "Work No. 8",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-8/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1/crossheading/associated-development"
    },
    {
      "path": "schedule/1/paragraph/9",
      "kind": "paragraph",
      "number": "9",
      "heading": "Work No. 9",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-9/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1/crossheading/associated-development"
    },
    {
      "path": "schedule/1/paragraph/10",
      "kind": "paragraph",
      "number": "10",
      "heading": "Work No. 10",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-10/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1/crossheading/associated-development"
    },
    {
      "path": "schedule/1/part/1/crossheading/further-associated-development",
      "kind": "crossheading",
      "number": null,
      "heading": "Further associated development",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1"
    },
    {
      "path": "schedule/1/paragraph/11",
      "kind": "paragraph",
      "number": "11",
      "heading": null,
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-11/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/1/crossheading/further-associated-development"
    },
    {
      "path": "schedule/1/part/2",
      "kind": "part",
      "number": "2",
      "heading": "ANCILLARY WORKS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1"
    },
    {
      "path": "schedule/1/paragraph/12",
      "kind": "paragraph",
      "number": "12",
      "heading": null,
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-12/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/1/part/2"
    },
    {
      "path": "schedule/2",
      "kind": "schedule",
      "number": "2",
      "heading": "REQUIREMENTS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/2/paragraph/1",
      "kind": "paragraph",
      "number": "1",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/2",
      "kind": "paragraph",
      "number": "2",
      "heading": "Time limit for beginning of the authorised project",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-2/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/3",
      "kind": "paragraph",
      "number": "3",
      "heading": "Parts of the authorised project",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-3/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/4",
      "kind": "paragraph",
      "number": "4",
      "heading": "Detailed approval",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-4/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/5",
      "kind": "paragraph",
      "number": "5",
      "heading": "Phasing",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-5/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/6",
      "kind": "paragraph",
      "number": "6",
      "heading": "Construction environmental management plan",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-6/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/7",
      "kind": "paragraph",
      "number": "7",
      "heading": "Construction traffic management plan",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-7/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/8",
      "kind": "paragraph",
      "number": "8",
      "heading": "Highway works",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-8/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/9",
      "kind": "paragraph",
      "number": "9",
      "heading": "Construction hours",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-9/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/10",
      "kind": "paragraph",
      "number": "10",
      "heading": "Landscape and ecology management plan",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-10/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/11",
      "kind": "paragraph",
      "number": "11",
      "heading": "Woodland compensation plan",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-11/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/12",
      "kind": "paragraph",
      "number": "12",
      "heading": "Surface water drainage",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-12/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/13",
      "kind": "paragraph",
      "number": "13",
      "heading": "Flood risk assessment",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-13/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/14",
      "kind": "paragraph",
      "number": "14",
      "heading": "Queens Road residential properties",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-14/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/15",
      "kind": "paragraph",
      "number": "15",
      "heading": "Contaminated land",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-15/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/16",
      "kind": "paragraph",
      "number": "16",
      "heading": "External lighting",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-16/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/17",
      "kind": "paragraph",
      "number": "17",
      "heading": "Control of noise during operational use",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-17/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/18",
      "kind": "paragraph",
      "number": "18",
      "heading": "Decommissioning environmental management plan",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-18/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/19",
      "kind": "paragraph",
      "number": "19",
      "heading": "Operational travel plan",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-19/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/20",
      "kind": "paragraph",
      "number": "20",
      "heading": "Operational phase flood emergency response plans",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-20/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/2"
    },
    {
      "path": "schedule/2/paragraph/21",
      "kind": "paragraph",
      "number": "21",
      "heading": "Flood Defence Agreement",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-21/enacted",
      "extent": "E+W+S",
      "status": "repealed",
      "parent": "schedule/2"
    },
    {
      "path": "schedule/3",
      "kind": "schedule",
      "number": "3",
      "heading": "DEEMED MARINE LICENCE",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/3/part/1",
      "kind": "part",
      "number": "1",
      "heading": "GENERAL",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3"
    },
    {
      "path": "schedule/3/paragraph/1",
      "kind": "paragraph",
      "number": "1",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/1"
    },
    {
      "path": "schedule/3/paragraph/2",
      "kind": "paragraph",
      "number": "2",
      "heading": "Contacts",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-2/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/1"
    },
    {
      "path": "schedule/3/paragraph/3",
      "kind": "paragraph",
      "number": "3",
      "heading": "Licensed marine activities",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-3/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/1"
    },
    {
      "path": "schedule/3/paragraph/4",
      "kind": "paragraph",
      "number": "4",
      "heading": "Licence to dredge and deposit",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-4/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/1"
    },
    {
      "path": "schedule/3/paragraph/5",
      "kind": "paragraph",
      "number": "5",
      "heading": "Details of licensed marine activities",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-5/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/1"
    },
    {
      "path": "schedule/3/part/2",
      "kind": "part",
      "number": "2",
      "heading": "CONDITIONS APPLYING TO ALL LICENSABLE ACTIVITIES",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3"
    },
    {
      "path": "schedule/3/part/2/chapter/1",
      "kind": "chapter",
      "number": null,
      "heading": "General",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2"
    },
    {
      "path": "schedule/3/paragraph/6",
      "kind": "paragraph",
      "number": "6",
      "heading": null,
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-6/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/1"
    },
    {
      "path": "schedule/3/part/2/chapter/2",
      "kind": "chapter",
      "number": null,
      "heading": "Before licensed activities",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2"
    },
    {
      "path": "schedule/3/paragraph/7",
      "kind": "paragraph",
      "number": "7",
      "heading": "Notifications regarding licensed activities",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-7/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2"
    },
    {
      "path": "schedule/3/paragraph/8",
      "kind": "paragraph",
      "number": "8",
      "heading": "Construction environmental management plan",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-8/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2"
    },
    {
      "path": "schedule/3/paragraph/9",
      "kind": "paragraph",
      "number": "9",
      "heading": "Sediment sampling",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-9/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2"
    },
    {
      "path": "schedule/3/paragraph/10",
      "kind": "paragraph",
      "number": "10",
      "heading": "Agents, contractors and sub-contractors",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-10/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2"
    },
    {
      "path": "schedule/3/paragraph/11",
      "kind": "paragraph",
      "number": "11",
      "heading": "Cold weather construction restriction strategy",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-11/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2"
    },
    {
      "path": "schedule/3/paragraph/12",
      "kind": "paragraph",
      "number": "12",
      "heading": "Marine Noise Registry",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-12/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2"
    },
    {
      "path": "schedule/3/paragraph/13",
      "kind": "paragraph",
      "number": "13",
      "heading": "Marine written scheme of archaeological investigation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-13/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2"
    },
    {
      "path": "schedule/3/part/2/chapter/2/crossheading/during-licensed-activities",
      "kind": "crossheading",
      "number": null,
      "heading": "During licensed activities",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2"
    },
    {
      "path": "schedule/3/paragraph/14",
      "kind": "paragraph",
      "number": "14",
      "heading": "Flood risk assessment",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-14/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2/crossheading/during-licensed-activities"
    },
    {
      "path": "schedule/3/paragraph/15",
      "kind": "paragraph",
      "number": "15",
      "heading": "Construction environmental management plan",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-15/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2/crossheading/during-licensed-activities"
    },
    {
      "path": "schedule/3/paragraph/16",
      "kind": "paragraph",
      "number": "16",
      "heading": "Piling and marine construction works",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-16/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2/crossheading/during-licensed-activities"
    },
    {
      "path": "schedule/3/paragraph/17",
      "kind": "paragraph",
      "number": "17",
      "heading": "Marine written scheme of archaeological investigation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-17/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2/crossheading/during-licensed-activities"
    },
    {
      "path": "schedule/3/paragraph/18",
      "kind": "paragraph",
      "number": "18",
      "heading": "Concrete and cement",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-18/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2/crossheading/during-licensed-activities"
    },
    {
      "path": "schedule/3/paragraph/19",
      "kind": "paragraph",
      "number": "19",
      "heading": "Coatings and treatment",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-19/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2/crossheading/during-licensed-activities"
    },
    {
      "path": "schedule/3/paragraph/20",
      "kind": "paragraph",
      "number": "20",
      "heading": "Pollution and spills",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-20/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2/crossheading/during-licensed-activities"
    },
    {
      "path": "schedule/3/paragraph/21",
      "kind": "paragraph",
      "number": "21",
      "heading": "Disposal at sea",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-21/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2/crossheading/during-licensed-activities"
    },
    {
      "path": "schedule/3/paragraph/22",
      "kind": "paragraph",
      "number": "22",
      "heading": "Dropped objects",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-22/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2/crossheading/during-licensed-activities"
    },
    {
      "path": "schedule/3/paragraph/23",
      "kind": "paragraph",
      "number": "23",
      "heading": "Notice to Mariners",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-23/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/2/chapter/2/crossheading/during-licensed-activities"
    },
    {
      "path": "schedule/3/part/3",
      "kind": "part",
      "number": "3",
      "heading": "PROCEDURE FOR THE DISCHARGE OF CONDITIONS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3"
    },
    {
      "path": "schedule/3/paragraph/24",
      "kind": "paragraph",
      "number": "24",
      "heading": "Approvals and appeals",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-24/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/3/part/3"
    },
    {
      "path": "schedule/4",
      "kind": "schedule",
      "number": "4",
      "heading": "STREETS SUBJECT TO STREET WORKS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/5",
      "kind": "schedule",
      "number": "5",
      "heading": "ALTERATION OF STREETS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/5/part/1",
      "kind": "part",
      "number": "1",
      "heading": "PERMANENT ALTERATION OF LAYOUT",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-5/part-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/5"
    },
    {
      "path": "schedule/5/part/2",
      "kind": "part",
      "number": "2",
      "heading": "TEMPORARY ALTERATION OF LAYOUT",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-5/part-2/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/5"
    },
    {
      "path": "schedule/6",
      "kind": "schedule",
      "number": "6",
      "heading": "PERMANENT STOPPING UP OF HIGHWAYS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/7",
      "kind": "schedule",
      "number": "7",
      "heading": "PUBLIC RIGHTS OF WAY TO BE PERMANENTLY STOPPED UP",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/8",
      "kind": "schedule",
      "number": "8",
      "heading": "TEMPORARY RESTRICTION OR ALTERATION, ETC. OF THE USE OF STREETS OR PUBLIC RIGHTS OF WAY",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/8/part/1",
      "kind": "part",
      "number": "1",
      "heading": "TEMPORARY PROHIBITION OR RESTRICTION OF THE USE OR DIVERSION OF STREETS OR PUBLIC RIGHTS OF WAY",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-8/part-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8"
    },
    {
      "path": "schedule/8/part/2",
      "kind": "part",
      "number": "2",
      "heading": "TEMPORARY USE OF MOTOR VEHICLES ON PUBLIC RIGHTS OF WAY",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-8/part-2/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/8"
    },
    {
      "path": "schedule/9",
      "kind": "schedule",
      "number": "9",
      "heading": "ACCESS TO WORKS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/9/part/1",
      "kind": "part",
      "number": "1",
      "heading": "PERMANENT MEANS OF ACCESS TO WORKS",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-9/part-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/9"
    },
    {
      "path": "schedule/9/part/2",
      "kind": "part",
      "number": "2",
      "heading": "TEMPORARY MEANS OF ACCESS TO WORKS",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-9/part-2/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/9"
    },
    {
      "path": "schedule/10",
      "kind": "schedule",
      "number": "10",
      "heading": "TRAFFIC REGULATION MEASURES",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/10/part/1",
      "kind": "part",
      "number": "1",
      "heading": "PERMANENT SPEED LIMITS",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-10/part-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/10"
    },
    {
      "path": "schedule/10/part/2",
      "kind": "part",
      "number": "2",
      "heading": "TEMPORARY PROHIBITION OF PARKING",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-10/part-2/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/10"
    },
    {
      "path": "schedule/10/part/3",
      "kind": "part",
      "number": "3",
      "heading": "TEMPORARY ROAD CLOSURES",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-10/part-3/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/10"
    },
    {
      "path": "schedule/10/part/4",
      "kind": "part",
      "number": "4",
      "heading": "PRIORITY OF VEHICULAR TRAFFIC",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-10/part-4/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/10"
    },
    {
      "path": "schedule/11",
      "kind": "schedule",
      "number": "11",
      "heading": "MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR THE CREATION OF NEW RIGHTS AND IMPOSITION OF NEW RESTRICTIVE COVENANTS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/11/paragraph/1",
      "kind": "paragraph",
      "number": "1",
      "heading": "Compensation enactments",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-11/paragraph-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/11"
    },
    {
      "path": "schedule/11/paragraph/2",
      "kind": "paragraph",
      "number": "2",
      "heading": "Compensation enactments",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-11/paragraph-2/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/11"
    },
    {
      "path": "schedule/11/paragraph/3",
      "kind": "paragraph",
      "number": "3",
      "heading": "Compensation enactments",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-11/paragraph-3/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/11"
    },
    {
      "path": "schedule/11/paragraph/4",
      "kind": "paragraph",
      "number": "4",
      "heading": "Application of the 1965 Act",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-11/paragraph-4/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/11"
    },
    {
      "path": "schedule/12",
      "kind": "schedule",
      "number": "12",
      "heading": "LAND IN WHICH ONLY NEW RIGHTS AND RESTRICTIVE COVENANTS, ETC. MAY BE ACQUIRED",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/13",
      "kind": "schedule",
      "number": "13",
      "heading": "LAND OF WHICH ONLY TEMPORARY POSSESSION MAY BE TAKEN",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/14",
      "kind": "schedule",
      "number": "14",
      "heading": "PROTECTIVE PROVISIONS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/14/part/1",
      "kind": "part",
      "number": "1",
      "heading": "FOR THE PROTECTION OF THE STATUTORY CONSERVANCY AND NAVIGATION AUTHORITY FOR THE HUMBER",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14"
    },
    {
      "path": "schedule/14/paragraph/1",
      "kind": "paragraph",
      "number": "1",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/2",
      "kind": "paragraph",
      "number": "2",
      "heading": "General",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-2/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/3",
      "kind": "paragraph",
      "number": "3",
      "heading": "Approval of detailed design of tidal works",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-3/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/4",
      "kind": "paragraph",
      "number": "4",
      "heading": "Commencement of tidal works",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-4/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/5",
      "kind": "paragraph",
      "number": "5",
      "heading": "Discharges, etc.",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-5/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/6",
      "kind": "paragraph",
      "number": "6",
      "heading": "Obstruction in river",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-6/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/7",
      "kind": "paragraph",
      "number": "7",
      "heading": "Removal, etc. of the Statutory Conservancy and Navigation Authority’s moorings and buoys",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-7/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/8",
      "kind": "paragraph",
      "number": "8",
      "heading": "Navigational lights, buoys, etc.",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-8/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/9",
      "kind": "paragraph",
      "number": "9",
      "heading": "Removal of temporary works",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-9/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/10",
      "kind": "paragraph",
      "number": "10",
      "heading": "Protective action",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-10/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/11",
      "kind": "paragraph",
      "number": "11",
      "heading": "Abandoned or decayed works",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-11/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/12",
      "kind": "paragraph",
      "number": "12",
      "heading": "Facilities for navigation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-12/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/13",
      "kind": "paragraph",
      "number": "13",
      "heading": "Sedimentation, etc. and remedial action",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-13/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/14",
      "kind": "paragraph",
      "number": "14",
      "heading": "Indemnity",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-14/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/15",
      "kind": "paragraph",
      "number": "15",
      "heading": "Statutory functions",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-15/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/16",
      "kind": "paragraph",
      "number": "16",
      "heading": "Operating procedures",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-16/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/17",
      "kind": "paragraph",
      "number": "17",
      "heading": "Removal of wrecks and obstructions, etc.",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-17/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/paragraph/18",
      "kind": "paragraph",
      "number": "18",
      "heading": "Oil spillage plan",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-18/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/1"
    },
    {
      "path": "schedule/14/part/2",
      "kind": "part",
      "number": "2",
      "heading": "FOR THE PROTECTION OF THE ENVIRONMENT AGENCY",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14"
    },
    {
      "path": "schedule/14/paragraph/19",
      "kind": "paragraph",
      "number": "19",
      "heading": "Application",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-19/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/20",
      "kind": "paragraph",
      "number": "20",
      "heading": "Definitions",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-20/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/21",
      "kind": "paragraph",
      "number": "21",
      "heading": "Crossing flood management infrastructure",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-21/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/22",
      "kind": "paragraph",
      "number": "22",
      "heading": "Submission and approval of plans",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-22/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/23",
      "kind": "paragraph",
      "number": "23",
      "heading": "Construction of protective works",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-23/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/24",
      "kind": "paragraph",
      "number": "24",
      "heading": "Timing of works and service of notices",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-24/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/25",
      "kind": "paragraph",
      "number": "25",
      "heading": "Works not in accordance with this Part of this Schedule",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-25/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/26",
      "kind": "paragraph",
      "number": "26",
      "heading": "Maintenance of works during construction",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-26/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/27",
      "kind": "paragraph",
      "number": "27",
      "heading": "Remediating impaired drainage work",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-27/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/28",
      "kind": "paragraph",
      "number": "28",
      "heading": "Agency access",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-28/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/29",
      "kind": "paragraph",
      "number": "29",
      "heading": "Free passage of fish",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-29/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/30",
      "kind": "paragraph",
      "number": "30",
      "heading": "Outfall channels",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-30/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/31",
      "kind": "paragraph",
      "number": "31",
      "heading": "Costs and indemnity",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-31/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/paragraph/32",
      "kind": "paragraph",
      "number": "32",
      "heading": "Disputes",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-32/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/2"
    },
    {
      "path": "schedule/14/part/3",
      "kind": "part",
      "number": "3",
      "heading": "FOR THE PROTECTION OF NORTHERN POWERGRID",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14"
    },
    {
      "path": "schedule/14/paragraph/33",
      "kind": "paragraph",
      "number": "33",
      "heading": "Application",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-33/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/3"
    },
    {
      "path": "schedule/14/paragraph/34",
      "kind": "paragraph",
      "number": "34",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-34/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/3"
    },
    {
      "path": "schedule/14/paragraph/35",
      "kind": "paragraph",
      "number": "35",
      "heading": "Acquisition of land",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-35/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/3"
    },
    {
      "path": "schedule/14/paragraph/36",
      "kind": "paragraph",
      "number": "36",
      "heading": "Removal of apparatus",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-36/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/3"
    },
    {
      "path": "schedule/14/paragraph/37",
      "kind": "paragraph",
      "number": "37",
      "heading": "Facilities and rights for alternative apparatus",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-37/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/3"
    },
    {
      "path": "schedule/14/paragraph/38",
      "kind": "paragraph",
      "number": "38",
      "heading": "Retained apparatus",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-38/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/3"
    },
    {
      "path": "schedule/14/paragraph/39",
      "kind": "paragraph",
      "number": "39",
      "heading": "Expenses and costs",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-39/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/3"
    },
    {
      "path": "schedule/14/paragraph/40",
      "kind": "paragraph",
      "number": "40",
      "heading": "Damage to property and other losses",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-40/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/3"
    },
    {
      "path": "schedule/14/paragraph/41",
      "kind": "paragraph",
      "number": "41",
      "heading": "Enactments and agreements",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-41/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/3"
    },
    {
      "path": "schedule/14/paragraph/42",
      "kind": "paragraph",
      "number": "42",
      "heading": "Cooperation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-42/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/3"
    },
    {
      "path": "schedule/14/paragraph/43",
      "kind": "paragraph",
      "number": "43",
      "heading": "Miscellaneous",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-43/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/3"
    },
    {
      "path": "schedule/14/paragraph/44",
      "kind": "paragraph",
      "number": "44",
      "heading": "Miscellaneous",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-44/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/3"
    },
    {
      "path": "schedule/14/part/4",
      "kind": "part",
      "number": "4",
      "heading": "FOR THE PROTECTION OF ANGLIAN WATER",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14"
    },
    {
      "path": "schedule/14/paragraph/45",
      "kind": "paragraph",
      "number": "45",
      "heading": "Application",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-45/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/paragraph/46",
      "kind": "paragraph",
      "number": "46",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-46/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/paragraph/47",
      "kind": "paragraph",
      "number": "47",
      "heading": "Protective works to buildings",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-47/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/paragraph/48",
      "kind": "paragraph",
      "number": "48",
      "heading": "Acquisition of land",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-48/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/paragraph/49",
      "kind": "paragraph",
      "number": "49",
      "heading": "Removal of apparatus",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-49/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/paragraph/50",
      "kind": "paragraph",
      "number": "50",
      "heading": "Facilities and rights for alternative apparatus",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-50/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/paragraph/51",
      "kind": "paragraph",
      "number": "51",
      "heading": "Retained apparatus",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-51/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/paragraph/52",
      "kind": "paragraph",
      "number": "52",
      "heading": "Expenses and costs",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-52/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/paragraph/53",
      "kind": "paragraph",
      "number": "53",
      "heading": "Expenses and costs",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-53/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/paragraph/54",
      "kind": "paragraph",
      "number": "54",
      "heading": "Cooperation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-54/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/paragraph/55",
      "kind": "paragraph",
      "number": "55",
      "heading": "Cooperation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-55/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/paragraph/56",
      "kind": "paragraph",
      "number": "56",
      "heading": "Enactments and agreements",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-56/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/paragraph/57",
      "kind": "paragraph",
      "number": "57",
      "heading": "Substitution of agreed periods of time",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-57/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/4"
    },
    {
      "path": "schedule/14/part/5",
      "kind": "part",
      "number": "5",
      "heading": "FOR THE PROTECTION OF NETWORK RAIL",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14"
    },
    {
      "path": "schedule/14/paragraph/58",
      "kind": "paragraph",
      "number": "58",
      "heading": "Application",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-58/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/59",
      "kind": "paragraph",
      "number": "59",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-59/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/60",
      "kind": "paragraph",
      "number": "60",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-60/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/61",
      "kind": "paragraph",
      "number": "61",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-61/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/62",
      "kind": "paragraph",
      "number": "62",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-62/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/63",
      "kind": "paragraph",
      "number": "63",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-63/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/64",
      "kind": "paragraph",
      "number": "64",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-64/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/65",
      "kind": "paragraph",
      "number": "65",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-65/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/66",
      "kind": "paragraph",
      "number": "66",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-66/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/67",
      "kind": "paragraph",
      "number": "67",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-67/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/68",
      "kind": "paragraph",
      "number": "68",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-68/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/69",
      "kind": "paragraph",
      "number": "69",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-69/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/70",
      "kind": "paragraph",
      "number": "70",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-70/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/71",
      "kind": "paragraph",
      "number": "71",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-71/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/72",
      "kind": "paragraph",
      "number": "72",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-72/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/73",
      "kind": "paragraph",
      "number": "73",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-73/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/74",
      "kind": "paragraph",
      "number": "74",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-74/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/75",
      "kind": "paragraph",
      "number": "75",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-75/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/76",
      "kind": "paragraph",
      "number": "76",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-76/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/77",
      "kind": "paragraph",
      "number": "77",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-77/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/paragraph/78",
      "kind": "paragraph",
      "number": "78",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-78/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/5"
    },
    {
      "path": "schedule/14/part/6",
      "kind": "part",
      "number": "6",
      "heading": "FOR THE PROTECTION OF NORTH EAST LINCOLNSHIRE COUNCIL (AS LEAD LOCAL FLOOD AUTHORITY)",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14"
    },
    {
      "path": "schedule/14/paragraph/79",
      "kind": "paragraph",
      "number": "79",
      "heading": "Application",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-79/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/6"
    },
    {
      "path": "schedule/14/paragraph/80",
      "kind": "paragraph",
      "number": "80",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-80/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/6"
    },
    {
      "path": "schedule/14/paragraph/81",
      "kind": "paragraph",
      "number": "81",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-81/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/6"
    },
    {
      "path": "schedule/14/paragraph/82",
      "kind": "paragraph",
      "number": "82",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-82/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/6"
    },
    {
      "path": "schedule/14/paragraph/83",
      "kind": "paragraph",
      "number": "83",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-83/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/6"
    },
    {
      "path": "schedule/14/paragraph/84",
      "kind": "paragraph",
      "number": "84",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-84/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/6"
    },
    {
      "path": "schedule/14/paragraph/85",
      "kind": "paragraph",
      "number": "85",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-85/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/6"
    },
    {
      "path": "schedule/14/paragraph/86",
      "kind": "paragraph",
      "number": "86",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-86/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/6"
    },
    {
      "path": "schedule/14/paragraph/87",
      "kind": "paragraph",
      "number": "87",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-87/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/6"
    },
    {
      "path": "schedule/14/paragraph/88",
      "kind": "paragraph",
      "number": "88",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-88/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/6"
    },
    {
      "path": "schedule/14/paragraph/89",
      "kind": "paragraph",
      "number": "89",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-89/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/6"
    },
    {
      "path": "schedule/14/part/7",
      "kind": "part",
      "number": "7",
      "heading": "FOR THE PROTECTION OF CADENT GAS LIMITED AS GAS UNDERTAKER",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14"
    },
    {
      "path": "schedule/14/paragraph/90",
      "kind": "paragraph",
      "number": "90",
      "heading": "Application",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-90/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/91",
      "kind": "paragraph",
      "number": "91",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-91/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/92",
      "kind": "paragraph",
      "number": "92",
      "heading": "On street apparatus",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-92/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/93",
      "kind": "paragraph",
      "number": "93",
      "heading": "Apparatus of Cadent in stopped up streets",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-93/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/94",
      "kind": "paragraph",
      "number": "94",
      "heading": "Protective works to buildings",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-94/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/95",
      "kind": "paragraph",
      "number": "95",
      "heading": "Acquisition of land",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-95/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/96",
      "kind": "paragraph",
      "number": "96",
      "heading": "Removal of apparatus",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-96/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/97",
      "kind": "paragraph",
      "number": "97",
      "heading": "Facilities and rights for alternative apparatus",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-97/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/98",
      "kind": "paragraph",
      "number": "98",
      "heading": "Retained apparatus: protection of Cadent",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-98/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/99",
      "kind": "paragraph",
      "number": "99",
      "heading": "Expenses",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-99/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/100",
      "kind": "paragraph",
      "number": "100",
      "heading": "Indemnity",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-100/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/101",
      "kind": "paragraph",
      "number": "101",
      "heading": "Enactments and agreements",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-101/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/102",
      "kind": "paragraph",
      "number": "102",
      "heading": "Co-operation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-102/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/103",
      "kind": "paragraph",
      "number": "103",
      "heading": "Co-operation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-103/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/104",
      "kind": "paragraph",
      "number": "104",
      "heading": "Access",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-104/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/105",
      "kind": "paragraph",
      "number": "105",
      "heading": "Arbitration",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-105/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/paragraph/106",
      "kind": "paragraph",
      "number": "106",
      "heading": "Notices",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-106/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/7"
    },
    {
      "path": "schedule/14/part/8",
      "kind": "part",
      "number": "8",
      "heading": "FOR THE PROTECTION OF OPERATORS OF ELECTRONIC COMMUNICATIONS CODE NETWORKS",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14"
    },
    {
      "path": "schedule/14/paragraph/107",
      "kind": "paragraph",
      "number": "107",
      "heading": "Application",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-107/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/8"
    },
    {
      "path": "schedule/14/paragraph/108",
      "kind": "paragraph",
      "number": "108",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-108/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/8"
    },
    {
      "path": "schedule/14/paragraph/109",
      "kind": "paragraph",
      "number": "109",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-109/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/8"
    },
    {
      "path": "schedule/14/paragraph/110",
      "kind": "paragraph",
      "number": "110",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-110/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/8"
    },
    {
      "path": "schedule/14/paragraph/111",
      "kind": "paragraph",
      "number": "111",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-111/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/8"
    },
    {
      "path": "schedule/14/paragraph/112",
      "kind": "paragraph",
      "number": "112",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-112/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/8"
    },
    {
      "path": "schedule/14/part/9",
      "kind": "part",
      "number": "9",
      "heading": "FOR THE PROTECTION OF THE NORTH EAST LINDSEY DRAINAGE BOARD",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14"
    },
    {
      "path": "schedule/14/paragraph/113",
      "kind": "paragraph",
      "number": "113",
      "heading": "Application",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-113/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/9"
    },
    {
      "path": "schedule/14/paragraph/114",
      "kind": "paragraph",
      "number": "114",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-114/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/9"
    },
    {
      "path": "schedule/14/paragraph/115",
      "kind": "paragraph",
      "number": "115",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-115/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/9"
    },
    {
      "path": "schedule/14/paragraph/116",
      "kind": "paragraph",
      "number": "116",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-116/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/9"
    },
    {
      "path": "schedule/14/paragraph/117",
      "kind": "paragraph",
      "number": "117",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-117/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/9"
    },
    {
      "path": "schedule/14/paragraph/118",
      "kind": "paragraph",
      "number": "118",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-118/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/9"
    },
    {
      "path": "schedule/14/paragraph/119",
      "kind": "paragraph",
      "number": "119",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-119/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/9"
    },
    {
      "path": "schedule/14/paragraph/120",
      "kind": "paragraph",
      "number": "120",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-120/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/9"
    },
    {
      "path": "schedule/14/paragraph/121",
      "kind": "paragraph",
      "number": "121",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-121/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/9"
    },
    {
      "path": "schedule/14/paragraph/122",
      "kind": "paragraph",
      "number": "122",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-122/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/9"
    },
    {
      "path": "schedule/14/part/10",
      "kind": "part",
      "number": "10",
      "heading": "FOR THE PROTECTION OF CLDN PORTS KILLINGHOLME LIMITED",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14"
    },
    {
      "path": "schedule/14/paragraph/123",
      "kind": "paragraph",
      "number": "123",
      "heading": "Application",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-123/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/10"
    },
    {
      "path": "schedule/14/paragraph/124",
      "kind": "paragraph",
      "number": "124",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-124/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/10"
    },
    {
      "path": "schedule/14/paragraph/125",
      "kind": "paragraph",
      "number": "125",
      "heading": "Co-operation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-125/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/10"
    },
    {
      "path": "schedule/14/paragraph/126",
      "kind": "paragraph",
      "number": "126",
      "heading": "Notice and undue interference",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-126/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/10"
    },
    {
      "path": "schedule/14/paragraph/127",
      "kind": "paragraph",
      "number": "127",
      "heading": "Notice and undue interference",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-127/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/10"
    },
    {
      "path": "schedule/14/paragraph/128",
      "kind": "paragraph",
      "number": "128",
      "heading": "Indemnity",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-128/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/10"
    },
    {
      "path": "schedule/14/paragraph/129",
      "kind": "paragraph",
      "number": "129",
      "heading": "Statutory powers",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-129/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/10"
    },
    {
      "path": "schedule/14/paragraph/130",
      "kind": "paragraph",
      "number": "130",
      "heading": "Statutory powers",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-130/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/10"
    },
    {
      "path": "schedule/14/paragraph/131",
      "kind": "paragraph",
      "number": "131",
      "heading": "Arbitration",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-131/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/14/part/10"
    },
    {
      "path": "schedule/15",
      "kind": "schedule",
      "number": "15",
      "heading": "DOCUMENTS AND PLANS TO BE CERTIFIED",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/16",
      "kind": "schedule",
      "number": "16",
      "heading": "ARBITRATION RULES",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/16/paragraph/1",
      "kind": "paragraph",
      "number": "1",
      "heading": "Commencing an arbitration",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-16/paragraph-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/16"
    },
    {
      "path": "schedule/16/paragraph/2",
      "kind": "paragraph",
      "number": "2",
      "heading": "Time periods",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-16/paragraph-2/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/16"
    },
    {
      "path": "schedule/16/paragraph/3",
      "kind": "paragraph",
      "number": "3",
      "heading": "Timetable",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-16/paragraph-3/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/16"
    },
    {
      "path": "schedule/16/paragraph/4",
      "kind": "paragraph",
      "number": "4",
      "heading": "Procedure",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-16/paragraph-4/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/16"
    },
    {
      "path": "schedule/16/paragraph/5",
      "kind": "paragraph",
      "number": "5",
      "heading": "Arbitrator’s powers",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-16/paragraph-5/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/16"
    },
    {
      "path": "schedule/16/paragraph/6",
      "kind": "paragraph",
      "number": "6",
      "heading": "Costs",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-16/paragraph-6/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/16"
    },
    {
      "path": "schedule/16/paragraph/7",
      "kind": "paragraph",
      "number": "7",
      "heading": "Confidentiality",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-16/paragraph-7/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/16"
    },
    {
      "path": "schedule/17",
      "kind": "schedule",
      "number": "17",
      "heading": "PROCEDURE REGARDING CERTAIN APPROVALS, ETC.",
      "url": null,
      "extent": "E+W+S",
      "status": null,
      "parent": null
    },
    {
      "path": "schedule/17/paragraph/1",
      "kind": "paragraph",
      "number": "1",
      "heading": "Interpretation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-17/paragraph-1/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/17"
    },
    {
      "path": "schedule/17/paragraph/2",
      "kind": "paragraph",
      "number": "2",
      "heading": "Applications made under provisions of this Order",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-17/paragraph-2/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/17"
    },
    {
      "path": "schedule/17/paragraph/3",
      "kind": "paragraph",
      "number": "3",
      "heading": "Further information and consultation",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-17/paragraph-3/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/17"
    },
    {
      "path": "schedule/17/paragraph/4",
      "kind": "paragraph",
      "number": "4",
      "heading": "Appeals",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-17/paragraph-4/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/17"
    },
    {
      "path": "schedule/17/paragraph/5",
      "kind": "paragraph",
      "number": "5",
      "heading": "Fees",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-17/paragraph-5/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": "schedule/17"
    },
    {
      "path": "note",
      "kind": "note",
      "number": null,
      "heading": "Explanatory note",
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/note/enacted",
      "extent": "E+W+S",
      "status": null,
      "parent": null
    }
  ],
  "has_text": null,
  "pdfs": [
    {
      "title": "Printed copy",
      "main": true,
      "language": null,
      "date": "2025-02-18",
      "size": 923296,
      "url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/pdf/uksi_20250165_en.pdf",
      "source_url": "https://www.legislation.gov.uk/uksi/2025/165/pdfs/uksi_20250165_en.pdf"
    }
  ],
  "outstanding_effects": [],
  "made_under": [
    {
      "id": "ukpga/2008/29",
      "title": "Planning Act 2008",
      "url": "https://openlegislation.uk/planning-act-2008",
      "provisions": []
    }
  ],
  "changes_made_to": 315,
  "changes_made_to_url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/changes.json",
  "changes_made_by": 349,
  "changes_made_by_url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/changes/by-it.json",
  "instruments_made_under": 0,
  "instruments_made_under_url": "https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/instruments.json",
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/165",
    "retrieved_at": "2026-10-28T21:20:25.915436+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}