# The Associated British Ports (Immingham Green Energy Terminal) Order 2025, Paragraph 10: Work No. 10

Extent: E+W+S

Within the area shown on sheets 6 and 7 of the works plans as Work No. 10, the temporary modification of overhead cables and lines and the temporary removal of highway signage, lamp posts and other street furniture.

---
Source: https://www.legislation.gov.uk/uksi/2025/165/schedule/1/paragraph/10 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-10