Generally, works within the Order limits comprised in—
(a) surveying and setting-out;
(b) vegetation removal;
(c) planting;
(d) installation of demarcation fencing, stockproof fencing and heras fencing or similar to enable the establishment of construction areas;
(e) survey trenches and pits; and
(f) demobilisation of construction works.

---