# The Associated British Ports (Immingham Green Energy Terminal) Order 2025, Paragraph 4: Work No. 4

Extent: E+W+S

Within the area of land shown on sheet 4 of the works plans as Work No. 4, an underground culvert, containing pipelines, pipes, cables and other conducting media, with any required cathodic protection, under Laporte Road, to link Work Nos. 3 and 5 and including related surface works, fencing, excavations, back-filling and making good to the highway.

---
Source: https://www.legislation.gov.uk/uksi/2025/165/schedule/1/paragraph/4 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-1/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.