# The Associated British Ports (Immingham Green Energy Terminal) Order 2025, Paragraph 126: Notice and undue interference

Extent: E+W+S

The undertaker must inform CLdN in writing of the intended start date and the likely duration of the carrying out of the specified work at least 20 business days prior to the commencement of the specified work.

---