(1) Notwithstanding anything in the licences, the undertaker must during the construction of any specified works maintain in good repair and condition and free from obstruction any drainage work to which all of the following paragraphs apply, whether or not the drainage work is constructed under the powers conferred by this Order or is already in existence—
(a) The drainage work is within the Order limits;
(b) The drainage work is one to which the specified works in question relate or which they affect (in each case) in the manner set out in the meaning given to “specified works” in paragraph 19; and
(c) The drainage work in question falls within a temporary construction compound under the control of the undertaker.
(2) If a drainage work to which sub-paragraph (1) refers is not maintained to the reasonable satisfaction of the Agency on the terms of that sub-paragraph, the Agency may by notice in writing require the undertaker to repair and restore it, or any part of it, or (if the undertaker so elects and the Agency in writing consents, such consent not to be unreasonably withheld or delayed) to remove the drainage work and restore the site to its former condition, to such extent and within such limits as the Agency reasonably requires.
(3) Subject to sub-paragraph (4) if, within a reasonable period, being not less than 28 days beginning with the date on which a notice in respect of a drainage work to which sub-paragraph (1) refers is served under sub-paragraph (2) on the undertaker, the undertaker has failed to begin taking steps to comply with the requirements of the notice and has not subsequently made reasonably expeditious progress towards their implementation, the Agency may do what is necessary for such compliance and any reasonable expenditure incurred by the Agency in so doing is recoverable from the undertaker.
(4) In the event of any dispute as to the reasonableness of any requirement of a notice served under sub-paragraph (3) the Agency must not, except in the case of an emergency, exercise the powers conferred by sub-paragraph (3) until the dispute has been finally determined in accordance with paragraph 32 (disputes).
(5) This paragraph does not apply to any obstruction of a drainage work expressly authorised in plans or particulars approved in writing by the Agency or determined under paragraph 32 (disputes) and carried out in accordance with the provisions of this Part of this Schedule provided that any obstruction is removed as soon as reasonably practicable.

---
Source: https://www.legislation.gov.uk/uksi/2025/165/schedule/14/paragraph/26 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-26
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.