# The Associated British Ports (Immingham Green Energy Terminal) Order 2025, Paragraph 35: Acquisition of land

Extent: E+W+S

Regardless of any provision in this Order or anything shown on the land plans the undertaker must not acquire any apparatus or override any easement or other interest of Northern Powergrid otherwise than by agreement with Northern Powergrid, such agreement not to be unreasonably withheld or delayed.

---
Source: https://www.legislation.gov.uk/uksi/2025/165/schedule/14/paragraph/35 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-14/paragraph-35
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

