# The Associated British Ports (Immingham Green Energy Terminal) Order 2025, Paragraph 12: Surface water drainage

Extent: E+W+S

(1) No part of Work No. 1 outside of the UK marine area, Work Nos. 2, 3, 5 or 7 (except the clearance of trees or other vegetation from Long Strip) may be commenced until the drainage strategy for that part has been submitted to and approved by the relevant planning authority, following consultation with the Environment Agency and the Board on matters related to their respective functions.
(2) Any drainage strategy submitted and approved under sub-paragraph (1) must be substantially in accordance with the outline drainage strategy contained in appendix 18.B of the environmental statement.
(3) Each part of Work No. 1 outside of the UK marine area, Work Nos. 2, 3, 5 and 7 must be carried out in accordance with the drainage strategy approved under sub-paragraph (1) for that part, unless otherwise approved by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2025/165/schedule/2/paragraph/12 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-2/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.