Any application to the relevant planning authority pursuant to a paragraph of this Schedule in respect of a part of the authorised project must include a plan showing the part to which the application relates, the parts (if any) in respect of which an application pursuant to that paragraph has previously been approved by the relevant planning authority and the parts (if any) in respect of which the requirement for approval by the relevant planning authority pursuant to the paragraph remains to be satisfied.

---