# The Associated British Ports (Immingham Green Energy Terminal) Order 2025, Paragraph 23: Notice to Mariners

Extent: E+W+S

(1) Local mariners, fishermen’s organisations and the UK Hydrographic Office must be notified of any licensed activity or phase of licensed activity through a local Notice to Mariners.
(2) A Notice to Mariners must be issued at least 5 days before the commencement of each licensed activity or phase of licensed activity.
(3) The MMO and Maritime and Coastguard Agency must be sent a copy of the notification within 24 hours of issue. The Notice to Mariners must include—
(a) the start and end dates of the work;
(b) a summary of the works to be undertaken;
(c) the location of the works area, including coordinated in accordance with WGS84; and
(d) any markings of the works area that will be put in place.
(4) A copy of the notice must be provided to the MMO via MCMS within 24 hours of issue of a notice under sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2025/165/schedule/3/paragraph/23 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-23
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.