# The Associated British Ports (Immingham Green Energy Terminal) Order 2025, Paragraph 8: Construction environmental management plan

Extent: E+W+S

(1) No licensed activities may be commenced until a construction environmental management plan for them has been submitted to and approved by the MMO following consultation with the relevant planning authority, the Environment Agency and Natural England on matters related to their function; and the submitted construction environmental management plan must be in accordance with the outline construction environmental management plan, unless otherwise approved in writing by the MMO.
(2) Any construction environmental management plan submitted pursuant to sub-paragraph (1) and any construction environmental management plan submitted pursuant to paragraph 6(1) of Schedule 2 (requirements) of the Order may be comprised in the same document or separate documents.

---
Source: https://www.legislation.gov.uk/uksi/2025/165/schedule/3/paragraph/8 (the official version)
Page: https://openlegislation.uk/associated-british-ports-immingham-green-energy-terminal-order-2025/schedule-3/paragraph-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.