# The Associated British Ports (Immingham Green Energy Terminal) Order 2025, Paragraph 9: Sediment sampling

Extent: E+W+S

(1) Any sediment sampling analyses undertaken by a laboratory validated by the MMO and approved by the MMO as part of either the 2023 sediment sampling plan or any further sediment sampling plan are valid for a period of 3 years from the date when those analyses were undertaken.
(2) Where the validity period for sediment sampling analyses set out in sub-paragraph (1) above expires, the undertaker must submit a further sediment sampling plan request to the MMO for its approval and any sediment sampling analyses from such further sediment sampling plan must be submitted to the MMO.

---