# The Awel y Môr Offshore Wind Farm Order 2023, Paragraph 2: Applications made under requirements

Extent: E+W

Where an application has been made to the relevant planning authority for any consent, agreement or approval required pursuant to a requirement included in this Order, the relevant planning authority must give notice to the undertaker of their decision, including the reasons, on the application, within a period of 13 weeks beginning with—
(a) the day immediately following that on which the application is received by the relevant planning authority; or
(b) such longer period as may be agreed by the undertaker and the relevant planning authority.

---