# The Awel y Môr Offshore Wind Farm Order 2023, Paragraph 17: Restoration of land used temporarily for construction

Extent: E+W

Any land landward of MLWS which is used temporarily for construction of the onshore works and not ultimately incorporated in permanent works or approved landscaping must be reinstated within six months of completion of the relevant stage of the onshore works in accordance with details submitted to and approved by the relevant planning authority under requirement 10 (code of construction practice).

---
Source: https://www.legislation.gov.uk/uksi/2023/1033/schedule/2/paragraph/17 (the official version)
Page: https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023/schedule-2/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.