# The Awel y Môr Offshore Wind Farm Order 2023, Paragraph 25: Wake effects

Extent: E+W

(1) No part of any wind turbine generator shall be erected as part of the authorised development until an assessment of any wake effects and subsequent design provisions to mitigate any such identified effects as far as possible has been submitted to and approved in writing by the Secretary of State, in order to mitigate the impact of the authorised development on the energy generation of Rhyl Flats Wind Farm. The assessment must be based on the scope of this Order as granted.
(2) The authorised development shall be carried out in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2023/1033/schedule/2/paragraph/25 (the official version)
Page: https://openlegislation.uk/awel-y-mor-offshore-wind-farm-order-2023/schedule-2/paragraph-25
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.