  "kind": "paragraph",
  "number": "8",
  "heading": "Provision of landscaping",
  "text": "(1) Work No. 31A must not be commenced until a written landscaping scheme and associated work programme in accordance with the outline landscape and ecology management plan for Work No. 31A has been submitted to and approved by the relevant planning authority following consultation with Natural Resources Wales as appropriate.\n(2) The written landscaping scheme must include details of all proposed hard and soft landscaping works including—\n(a) location, number, species, size and planting density of any proposed planting including any trees; and\n(b) implementation timetables for all landscaping works.\n(3) The written landscaping scheme and associated work programme must be carried out in accordance with the approved details.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 8 in force at 11.10.2023, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2023/1033/schedule/2/paragraph/8",
    "retrieved_at": "2026-10-28T21:40:22.905590+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}